โจ Most impactful changes
๐ฅ Import and create from Project Insights: Tasks and activities can be imported onto a workspace from the List, Activities and Constraint Log (Import Selected or drag rows onto the workspace; Hide already imported shows only whatโs missing). Tasks can be created in the List and constraints in the Constraint Log, in every context. The import dialog (+) is still available.
๐ Insights opens with the full project view: Inside a workspace, the workspace filter is no longer applied by default.
๐ Add connections from the task editor: The Add button on the Connections page creates predecessors, successors and parent/child links by searching the project, also from Project Insights.
๐ Plan lock and admin-only plan creation: Plans can be locked or admin locked; only workspace admins can create new plans.
๐ Import into the N/A swimlane: The N/A swimlane gets its own import dialog and filters; both plan import dialogs gain a Modified since filter.
๐ฅ Workspace roles in the Project Control Center: Workspace admins see the full Project CC, workspace editors see only Labels.
๐๏ธ 1. Central Task Database
- Tasks and constraints can also be created from Project Insights
- Import from the database via Project Insights or the import dialog (+), including Hide already imported, Import Selected, and drag and drop
๐ฆ 2. Task Visualization
- Focus mode: Type filter includes activities and activity milestones, State section has a Deleted option, removed teams no longer appear in the Team filter
- Searching the workspace also finds live task cards and centers on each match
- Move/copy tooltip while dragging (hold Alt to copy, release Alt to move)
- Progress indicator: progress bar or spinner, now also covering imports, uploads, PDF export and AI conversions
โ๏ธ 3. Task Editor
- Add dependencies dialog with Predecessor, Successor, Parent and Child, searchable by title, Hoylu ID or activity ID, also available in Project Insights
๐๏ธ 4. Plan Visualization
- Locking a plan: Lock (contributors and admins) and Admin lock (admins only); a locked plan canโt be moved, reordered or reconfigured
- Plan presets and โCreate plan from project tasksโ are now limited to workspace admins
- Linking a plan: Add new in the label category dropdown; confirmation skipped for empty plans
- Importing into a plan: separate N/A swimlane import, Modified since filter, label filter logic and deleted filter options
- Selecting elements in a swimlane: Select all / Select from here / Select to here (coming soon)
๐ 5. Project Insights
- Insights opens with the full project view inside a workspace
- Import and create tasks and constraints from Insights
- Filters: OR within a label category, AND across categories; new Tomorrow preset; the Constraint Log opens with Next 90 days by default; keys 1โ5 switch views
- List: view label and workspace column. WWP: grouping kept across views and share links; group labels stay visible on mobile. Activities: Upload XER, Enter to upload, import onto the workspace
๐ 6. Bulk Import & Workspace Sync
- Project Insights added as a second way to import, next to the import dialog
- โCreate plan from project tasksโ limited to workspace admins
โ๏ธ 7. Project Control Center & Labels
- Visible sections depend on the workspace role: admins see everything, editors see Labels only
- Team membership is managed by workspace admins
๐ 8. Permissions
- Project CC access, creating plans and admin locks depend on the workspace role
- Team membership managed by workspace admins
๐๏ธ 9. XER Import & P6 Integration
- Hierarchy connections drawn as straight lines, with their own visibility setting (Always / On select / hover / Never); parent and child links can be added from the task editor
- Activity Report: Upload XER, Enter to upload, and import activities onto the workspace