Video 1. Assistive Rescheduling.
As Tasks are being statused and moved along the Plan, you may encounter dependency conflicts, in which Assistive Rescheduling will be helpful.
Instead of manually dragging and dropping dependent Tasks onto new dates, Hoylu will provide you the option to resolve the conflict by moving Tasks for you so they can either be pushed to a later day or pulled to an earlier day.
Admin Settings
Following the same rules of the different Task statuses, only Tasks that are in an Unplanned or Planned state can be moved by Assistive Rescheduling, so if you would like to use this option for Tasks in a Committed state, a Workspace Admin must adjust these settings.
Figure 1. Admin Settings in Assistive Rescheduling Menu.
-
Select any Task(s) that you would like to use Assistive Rescheduling to adjust
-
Click on the Selection Settings button on the menu bar that appears
-
Click on the gear icon on the top right corner
- Click on the applicable switches to include the additional task status types in Assistive Rescheduling options
Assistive Rescheduling - Push
When you need to adjust downstream or successor Tasks due to delays, you can use Assistive Rescheduling to push them down the Timeline. Note that the adjustments you have made to the relationship type (Start-to-Start, Finish-to-Start, etc) and any lag or lead times will affect the movement of those Tasks.
Figure 2. Assistive Rescheduling to push dependent Tasks.
-
Select all Tasks in a sequence of downstream dependencies
-
Click on the selection options button on the left side of the menu bar as seen in Figure 2
- Click the Push conflicts to later... option on the list or press Ctrl + A on your keyboard as many times as needed in order to adjust the Tasks and remove conflicts
Assistive Rescheduling - Pull
In addition to pushing Tasks downstream due to delays, you have the option of using Assistive Rescheduling to pull Tasks to earlier dates to ensure meeting deadlines.
Figure 3. Assistive Rescheduling to pull Tasks.
-
Select all Tasks in a sequence of upstream dependencies
-
Click on the selections options buttons on the left side of the menu bar as seen in Figure 3
- Click the Pull conflicts to earlier... option on the list or press Ctrl + Shift + A on your keyboard as many times as needed in order to adjust the Tasks and remove conflicts
Comments
0 comments
Article is closed for comments.