Split Multi-Day Tasks
To facilitate daily huddles and updates, Hoylu offers the option to split Tasks with longer durations into smaller pieces for more detailed updates.
-
Right-click on a multi-day Task in the Plan
- In the Context Menu, click on Split
-
Decide how you would like to divide the Task (into one-day segments or two-day, three-day, etc) and type the number into the field
-
Confirm if you would like Hoylu to automatically add connections between the split-up Task via the checkbox on the bottom left corner of the window
- Click on the Split button (which will also show you the amount of Tasks you will see when you perform the Split)
Split Multi-Week Tasks
To have an accurate PPC reading every week, you can use two options to split multi-week Tasks so they can be statused accordingly: a manual separation using the indicators between mulit-week segments or the Split function.
Click on either the three-dot icon between the Task segments on a collapsed Week view or the triangular midpoints on expanded weeks to "break" the Task up.
-
Right-click on a multi-week Task in the Plan
- In the Context Menu, click on Split
-
Click on Split at the start of each option
-
Use the dropdown menu on the right to decide when you would like that week's segment to begin
-
Confirm if you would like Hoylu to automatically add connections between the split-up Tasks via the checkbox on the bottom left corner of the window
- Click on the Split button (which will also show you the amount of Tasks you will see when you perform the Split)